Research on calculation of post-construction transverse surface settlement caused by shield tunneling
|更新时间:2026-06-25
|
Research on calculation of post-construction transverse surface settlement caused by shield tunneling
Vol. 34, Issue S2, (2013)
作者机构:
浙江大学城市学院 土木工程系,杭州,310015
作者简介:
基金信息:
DOI:
CLC:U455
Online First:19 November 2013,
Published:2013
稿件说明:
移动端阅览
YANG Ze-fei, WEI Gang, LIN Lei-lei, et al. Research on calculation of post-construction transverse surface settlement caused by shield tunneling[J]. 2013, 34(S2).
DOI:
YANG Ze-fei, WEI Gang, LIN Lei-lei, et al. Research on calculation of post-construction transverse surface settlement caused by shield tunneling[J]. 2013, 34(S2).DOI:
Research on calculation of post-construction transverse surface settlement caused by shield tunneling
the post-construction surface settlement will be continued caused by shield tunneling. Based on past research
a calculation method of initial excess pore water pressure around the tunnel is put forward. By using layerwise summation method
the surface consolidation settlement can be got within disturbed region of excess pore water pressure dissipation. Combining with the surface settlement in tunnel construction phase
total transverse post-construction surface settlement is obtained. The total surface settlement after soil consolidation is proposed; and surface settlement rate changes over time are also studied. As is shown in analytical calculation
the calculated results of the transverse surface settlement curves are in good agreement with the field data; and they are also in accordance with the normal distribution law. The development of total surface settlement rate is in good agreement with the field data.