Study of method and effect of high-position drainage of tunnel in water-rich fault
|更新时间:2026-06-25
|
Study of method and effect of high-position drainage of tunnel in water-rich fault
Vol. 33, Issue 11, (2012)
作者机构:
西南交通大学 交通隧道工程教育部重点实验室,成都,610031
作者简介:
基金信息:
DOI:
CLC:U455
Online First:14 November 2012,
Published:2012
稿件说明:
移动端阅览
ZHANG Zhi-qiang, HE Ben-guo, WANG Zhi-jie, et al. Study of method and effect of high-position drainage of tunnel in water-rich fault[J]. 2012, 33(11).
DOI:
ZHANG Zhi-qiang, HE Ben-guo, WANG Zhi-jie, et al. Study of method and effect of high-position drainage of tunnel in water-rich fault[J]. 2012, 33(11).DOI:
Study of method and effect of high-position drainage of tunnel in water-rich fault
The construction of Daxiang mountain tunnel in water-rich fault has great risks of causing water bursting and mud gushing easily. High-position drainage can reduce water pressure ahead of working face effectively. By using field test and numerical simulation
under different water-level conditions
the interrelation between method of high-position drainage and stability of tunnel is studied; and the optimal plan of arrangement of high-position drainage pipes is put forward. Studies show that: maximum water pressure of Daxiang mountain tunnel in fault is up to 1.98 MPa. The tunnel can be constructed securely after drainage and the maximum water head is only 10 meters. Therefore
prevention of water bursting is mainly concentrated in the period of tunnel face excavation. The drain volume of drain pipes at vault is maximum. The closer drain pipes and arch foot are
the more poor drainage capacity is; and the density of drain pipes at vault should be higher than that at arch foot. In actual construction
for faster to reach drain effect
drain pipes at vault should be first to arranged
then at arch foot. Interrelation between number of drain pipes
drain volume and extrusion deformation of tunnel face is studied. According to economy and effect of hydrophobic reinforcement