Prediction approach of ground deformation induced by pipe jacking construction considering grouting pressure
|更新时间:2026-06-25
|
Prediction approach of ground deformation induced by pipe jacking construction considering grouting pressure
Vol. 33, Issue 1, (2012)
作者机构:
1. 上海交通大学 船舶海洋与建筑工程学院,上海,200240
2. 上海交通大学 国家海洋工程重点试验室,上海,200240
作者简介:
基金信息:
DOI:
CLC:TU443
Online First:17 January 2012,
Published:2012
稿件说明:
移动端阅览
LI Fang-nan, SHEN Shui-long, LUO Chun-yong. Prediction approach of ground deformation induced by pipe jacking construction considering grouting pressure[J]. 2012, 33(1).
DOI:
LI Fang-nan, SHEN Shui-long, LUO Chun-yong. Prediction approach of ground deformation induced by pipe jacking construction considering grouting pressure[J]. 2012, 33(1).DOI:
Prediction approach of ground deformation induced by pipe jacking construction considering grouting pressure
Prediction of ground deformation caused by pipe jacking is very important for safe construction. During the construction of pipe jacking
the ground deformation will be influenced by: ①the attitude of pipe jacking machine and the supporting pressure on excavation face; ②the jacking process and the course of changing pipes; ③the grouting process
etc.. To analyze the ground movement during the construction of pipe jacking
a numerical approach is proposed. The Mindlin solution to vertical and horizontal force is used to calculate the ground deformation induced by the face support pressure and the lateral friction resistance
respectively. The Sagaseta method is adopted to consider the ground loss induced by over excavation. A complex variable method proposed by Verruijt is used to simulate the ground movement caused by grouting. Then a 3-D analytical solutions for ground movements induced by pipe jacking is obtained and applied to a case study. The results indicate that considering the grouting pressure can simulate the ground deformation induced by pipe jacking reasonably.