Field measurement and analysis of working properties of abutment pile in deep silt foundation
|更新时间:2026-06-25
|
Field measurement and analysis of working properties of abutment pile in deep silt foundation
Vol. 32, Issue 11, (2011)
作者机构:
中南大学 土木工程学院,长沙,410075
作者简介:
基金信息:
DOI:
CLC:TU473
Online First:09 November 2011,
Published:2011
稿件说明:
移动端阅览
YUE Jian, LENG Wu-ming, NIE Ru-song, et al. Field measurement and analysis of working properties of abutment pile in deep silt foundation[J]. 2011, 32(11).
DOI:
YUE Jian, LENG Wu-ming, NIE Ru-song, et al. Field measurement and analysis of working properties of abutment pile in deep silt foundation[J]. 2011, 32(11).DOI:
Field measurement and analysis of working properties of abutment pile in deep silt foundation
The field measurement had been performed for one and a half years
which was aiming at the impact-cone concrete piles of the bridge abutments on the deep silt foundation. Before constructing the pile cap
during the period of building the abutment
constructing embankment near the transition section
constructing embankment of the transition section and after building the span beam
the abutment pile strain and the pore water pressure on pile side had been tested; and the pile deflection and the abutment inclination had been observed. Based on the measured data,the stress and deformation properties of the abutment pile are analyzed. The results show that: the abutment pile is compressed before constructing the pile cap; due to the interaction of superstructure and earth filling
the compressive strain of the front side of the pile body is remarkably different from that of the back side; after finishing subgrade filling
the maximum negative bending moment of the pile appears in the shallow position of the silt layer; and the maximum positive bending moment appears in the soft-hard soil juncture; the abutment inclination is rectified after constructing the span beam.