Mechanism study of abrupt deformation of underground powerhouse induced by excavation unloading under high in-situ stress
|更新时间:2026-06-25
|
Mechanism study of abrupt deformation of underground powerhouse induced by excavation unloading under high in-situ stress
Vol. 32, Issue 5, (2011)
作者机构:
1. 武汉大学 水资源与水电工程科学国家重点实验室,武汉,430072
2. 武汉大学 水工岩石力学教育部重点实验室,武汉,430072
作者简介:
基金信息:
DOI:
CLC:TU354
Online First:23 September 2011,
Published:2011
稿件说明:
移动端阅览
LUO Yi, LU Wen-bo, ZHOU Chuang-bing, et al. Mechanism study of abrupt deformation of underground powerhouse induced by excavation unloading under high in-situ stress[J]. 2011, 32(5).
DOI:
LUO Yi, LU Wen-bo, ZHOU Chuang-bing, et al. Mechanism study of abrupt deformation of underground powerhouse induced by excavation unloading under high in-situ stress[J]. 2011, 32(5).DOI:
Mechanism study of abrupt deformation of underground powerhouse induced by excavation unloading under high in-situ stress
The mechanism of abrupt large deformation in the sidewall of underground powerhouse is analyzed. The surrounding rock mass dynamic loosening is concerned as a main cause of abrupt deformation in underground powerhouse. Based on the monitored data at Pubugou hydropower station
numerical analysis is conducted with finite element method; and horizontal displacements induced by excavation load quasi-static and dynamic unloading are calculated respectively. The result itself and comparison to monitored data show that sliding and opening on structural surfaces induced by excavation load dynamic unloading are the major causes of abrupt large deformation in underground powerhouse
but which is not so obvious under quasi-static unloading. In actual projects
the transient effect of in-situ stress unloading should be considered; and the disturbance in the surrounding rock mass during each operation should be minimized to avoid potential abrupt large deformation