Risk assessment of water or mud inrush of karst tunnels based on analytic hierarchy process
|更新时间:2026-06-25
|
Risk assessment of water or mud inrush of karst tunnels based on analytic hierarchy process
Vol. 32, Issue 6, (2011)
作者机构:
1. 山东大学 岩土与结构工程研究中心,济南,250061
2. 中交一公局 桥隧工程有限公司,河北 高碑店,074000
作者简介:
基金信息:
DOI:
CLC:U45
Online First:21 June 2011,
Published:2011
稿件说明:
移动端阅览
XU Zhen-hao, LI Shu-cai, LI Li-ping, et al. Risk assessment of water or mud inrush of karst tunnels based on analytic hierarchy process[J]. 2011, 32(6).
DOI:
XU Zhen-hao, LI Shu-cai, LI Li-ping, et al. Risk assessment of water or mud inrush of karst tunnels based on analytic hierarchy process[J]. 2011, 32(6).DOI:
Risk assessment of water or mud inrush of karst tunnels based on analytic hierarchy process
In order to control the construction risk of karst tunnels
through statistical and theoretical analyses of relevant engineering projects
controlling factors and factors’ weight of water or mud inrush risks of karst tunnels are studied based on analytic hierarchy process; and a three-stage risk assessment and management method is proposed for the evaluation and controlling of construction risk of karst tunnels. Factors’ weight analysis results show that unfavorable geology
geological prediction
formation lithology and groundwater level are the main control ingredients of water or mud inrush risk. Macroscopic geological precursory information
monitoring measurement
contact zones of dissolvable and insoluble rock
geographic and geomorphic conditions
tunnel excavation and supporting are the minor significant factors; microcosmic precursory information
attitude of rock formation
layer and interlayer fissures
surrounding rock mass classification are the least important elements. The three-stage risk assessment method includes preliminary
secondary and dynamic assessment of water or mud inrush risk. Preliminary assessment is the evaluation of risk surroundings (karst hydrogeological and engineering geological conditions)
and it is carried out for the estimation of risk before the enactment of the construction program. Secondary assessment is the evaluation of risk surroundings and risk factors (construction factors)
and it is actualized for the appraisal of construction organization plan pre construction. Dynamic assessment is the evaluation of risk surroundings
risk factors and feedback information of risk management; and it is brought into operation for dynamic risk assessment and management. The three-stage risk evaluation and controlling process can be instantly
effectively
and accurately used for the management of construction risk of karst tunnels
and to realize dynamically amending and governing of risk. The research results are successfully applied to Jigongling Tunnel on the line of Fanba Expressway; and it is of consultant significance for similar engineerings.