Study on stability and reinforcement measures of an unstable rock masses of Xiluodu Hydropower station
|更新时间:2026-06-25
|
Study on stability and reinforcement measures of an unstable rock masses of Xiluodu Hydropower station
Vol. 29, Issue 5, (2008)
作者机构:
1. 重庆大学 土木工程学院,重庆,400045
2. 成都理工大学 地质灾害防治与地质环境保护国家重点实验室,成都,610059
作者简介:
基金信息:
DOI:
CLC:TU457
Online First:24 July 2013,
Published:2008
稿件说明:
移动端阅览
HUANG Da, HUANG Run-qiu, PEI Xiang-jun, et al. Study on stability and reinforcement measures of an unstable rock masses of Xiluodu Hydropower station[J]. 2008, 29(5).
DOI:
HUANG Da, HUANG Run-qiu, PEI Xiang-jun, et al. Study on stability and reinforcement measures of an unstable rock masses of Xiluodu Hydropower station[J]. 2008, 29(5).DOI:
Study on stability and reinforcement measures of an unstable rock masses of Xiluodu Hydropower station
Based on investigation on spot and geological analysis
an unstable rock masses of Xiloudu Hydropower Station may to be failure through two modes: shear-falling and rip-topple is proposed; and a mechanical model for calculation of stability by limit equilibrium theory is established; and the unstable rock masses deformation and failure characteristics are analyzed by numerical simulation. The results show: stability of the unstable rock masses is relatively bad if the failure mode is rip- topple
but is good if shear-falling. Based on stability analysis
the anchor reinforcement force is calculated as 12 306 kN when safety factor is 1.5 and the failure is rip-topple; and some reinforcement measures of the unstable rock masses are put for ward follows: fill hollow of rock and fill in cracks and prestressed anchor cables and anchor bolts combination reinforcement. The results of numerical simulation show that: effect of the reinforcement measures is better.