Sensitivity analysis of construction parameters of layered settlement
induced by double-O-tube shield
|更新时间:2026-06-25
|
Sensitivity analysis of construction parameters of layered settlement
induced by double-O-tube shield
Vol. 27, Issue S1, (2006)
作者机构:
1. 同济大学 地下建筑与工程系,上海,200092
2. 林同棪国际(重庆)工程咨询有限公司,重庆,401121
作者简介:
基金信息:
DOI:
CLC:TV554
Online First:15 December 2006,
Published:2006
稿件说明:
移动端阅览
SUN Tong-li, ZHANG Qing-he, HU Xiang-dong, et al. Sensitivity analysis of construction parameters of layered settlement
induced by double-O-tube shield[J]. 2006, 27(S1).
DOI:
SUN Tong-li, ZHANG Qing-he, HU Xiang-dong, et al. Sensitivity analysis of construction parameters of layered settlement
induced by double-O-tube shield[J]. 2006, 27(S1).DOI:
Sensitivity analysis of construction parameters of layered settlement
induced by double-O-tube shield
Based on the section tunnel construction of M6 rail transit project No.Ⅸ bid in Shanghai
the sensitivity analysis of construction parameters were carried out. During the construction
the parameters of cabin pressure
grout volume of shield tail
advance velocity were rectified designedly. The layered settlement of transverse and longitudinal sections induced by the construction of double-O-tube shield (DOT) in soft clay region was monitored continuously in-situ. The conclusion can be as reference for optimizing of the construction parameters
lessening the extent of environmental influence of soil engineering.