Site monitoring and analytical research on mechanical characteristics under construction partial press in double-arch tunnel
|更新时间:2026-06-25
|
Site monitoring and analytical research on mechanical characteristics under construction partial press in double-arch tunnel
Vol. 27, Issue 11, (2006)
作者机构:
西南交通大学 土木工程学院,成都,610031
作者简介:
基金信息:
DOI:
CLC:U456
Online First:04 December 2013,
Published:2006
稿件说明:
移动端阅览
SHEN Yu-sheng, GAO Bo. Site monitoring and analytical research on mechanical characteristics under construction partial press in double-arch tunnel[J]. 2006, 27(11).
DOI:
SHEN Yu-sheng, GAO Bo. Site monitoring and analytical research on mechanical characteristics under construction partial press in double-arch tunnel[J]. 2006, 27(11).DOI:
Site monitoring and analytical research on mechanical characteristics under construction partial press in double-arch tunnel
According to the Xiedipo double-arch tunnel engineering of the Yishui(Yibin—Shuifu) Highway
the key parts of structure force are monitored and analyzed by setting testing component in the tunnel; and during each period of construction the stress state of surrounding rock
bolt axial force
internal force of the middle-wall and internal forces of tunnel supporting structure are obtained under the condition of the constructional partial press. By analyzing tunnel mechanical characteristic under constructional partial press
the conclusions are drawn as follows: the most dangerous construction procedure of the tunnel structure force is from one side to the other side in the construction of the tunnel
that the bending moment direction of the middle-wall is always from one tunnel constructed lastly to the other tunnel constructed firstly in the double-arch tunnel. The monitored data and the experience can be for reference in the design