Forecast and analysis of surface subsidence of metro tunnel construction in mucky ground
|更新时间:2026-06-25
|
Forecast and analysis of surface subsidence of metro tunnel construction in mucky ground
Vol. 26, Issue 10, (2005)
作者机构:
石家庄铁道学院 土木工程分院,河北,石家庄,050043
作者简介:
基金信息:
DOI:
CLC:TU45
Online First:30 December 2013,
Published:2005
稿件说明:
移动端阅览
LIU Zhi-chun, LI Wen-jiang, ZHU Yong-quan. Forecast and analysis of surface subsidence of metro tunnel construction in mucky ground[J]. 2005, 26(10).
DOI:
LIU Zhi-chun, LI Wen-jiang, ZHU Yong-quan. Forecast and analysis of surface subsidence of metro tunnel construction in mucky ground[J]. 2005, 26(10).DOI:
Forecast and analysis of surface subsidence of metro tunnel construction in mucky ground
The Nanjing subway section between Zhujiang Road station and Gulou station passes through many ground buildings and dense underground pipes in soft-flowing mucky silty clay ground. The stratum is of high compressibility
low intensity
easy creeping
and no self-stability. The synthetical measure is adopted in this project
such as large pipe shed and small tremie as advance support and deep hole grouting at the work face
bench excavation and steel surpport
steel mesh and shotcrete support. In order to realize scientific decision and safety construction
calculation simulation is carried out according to the actual working condition to predict the surface subsidence. At the same time
subsidence monitoring is done during construction. The safety and smoothness of the tunnel construction is assured and the buildings are sound without any destruction.