Cause analysis of crack formation on the ash-ward slope of Zishan dam and measures of prevention and cure with grouting
|更新时间:2026-06-25
|
Cause analysis of crack formation on the ash-ward slope of Zishan dam and measures of prevention and cure with grouting
Vol. 25, Issue 4期 刊出日, (2004)
作者机构:
河南大学 土木建筑学院,河南,开封,475001
作者简介:
基金信息:
DOI:
CLC:TV698.2+31
Online First:17 July 2014,
Published:2004
稿件说明:
移动端阅览
LUO Chang-jun. Cause analysis of crack formation on the ash-ward slope of Zishan dam and measures of prevention and cure with grouting[J]. 2004, 25(4期 刊出日).
DOI:
LUO Chang-jun. Cause analysis of crack formation on the ash-ward slope of Zishan dam and measures of prevention and cure with grouting[J]. 2004, 25(4期 刊出日).DOI:
Cause analysis of crack formation on the ash-ward slope of Zishan dam and measures of prevention and cure with grouting
Owing to aerobic tank overtopping dam resulting in dam break
the drainage-seepage ditch on Zishan dam and non-sandy concrete surface of its ash-ward slope were partly damaged
that resulted in drainage amount was increased and ash was leaked sometimes on the exit of the drainage-seepage ditch and the cone of leak ash and water was formed on the inlet
a lot of cracks appeared in the beginning at the non-sandy concrete surface (rigid body) and in the sequel at the ash-ward slope surface (flexible body). The cause of formation of crack should be due to landslide. On the precondition of carrying out measures of saving and protecting the dam and choosing preventing and curing project
the feasible tests of filling grouting were done. The cracks were dealt with using the grouting. Then the dam had been gone through the very strong rainstorm in the current year. As yet
the dam was running normal. The results of grouting were better.