Study on flowing through screw conveyor during excavation with EPB shieldStudy on flowing through screw conveyor during excavation with EPB shield
|更新时间:2026-06-25
|
Study on flowing through screw conveyor during excavation with EPB shieldStudy on flowing through screw conveyor during excavation with EPB shield
Vol. 25, Issue 10期 刊出日, (2004)
作者机构:
河海大学 岩土工程研究所,江苏,南京,210098
作者简介:
基金信息:
DOI:
CLC:O357.3
Online First:25 July 2014,
Published:2004
稿件说明:
移动端阅览
QIN Jian-she, ZHU Wei. Study on flowing through screw conveyor during excavation with EPB shieldStudy on flowing through screw conveyor during excavation with EPB shield[J]. 2004, 25(10期 刊出日).
DOI:
QIN Jian-she, ZHU Wei. Study on flowing through screw conveyor during excavation with EPB shieldStudy on flowing through screw conveyor during excavation with EPB shield[J]. 2004, 25(10期 刊出日).DOI:
Study on flowing through screw conveyor during excavation with EPB shieldStudy on flowing through screw conveyor during excavation with EPB shield
When earth-pressure balance (EPB) shield is used in high permeability ground as well as high groundwater pressure
groundwater will flows through screw conveyor (Flowwing)
this will lead the loss of great quantity of groundwater and even the halt of excavation. Based on the steady-flow seepage theory and shield driving principle
a method for judge Flowing is provided
and a model for study the seepage of groundwater in chamber and screw conveyor is built to explain the mechanism of Flowing. With the model
the parameters such as soil condition
shield geometry
excavation instruction which relate with Flowing are analyzed and the results give some useful conclusions and suggestions to predict and avoid flowing. The model can also be used to calculate the discharge of groundwater.