Effects of time-effect of pile’s bearing capacity on pile-soil interaction and on settlement of pile-raft foundation
|更新时间:2026-06-25
|
Effects of time-effect of pile’s bearing capacity on pile-soil interaction and on settlement of pile-raft foundation
Vol. 24, Issue 1, (2003)
作者机构:
1. .天津大学 土木工程系,天津,300072
2. 天津市勘察院,天津,300191
作者简介:
基金信息:
DOI:
CLC:TU473
Online First:27 August 2014,
Published:2003
稿件说明:
移动端阅览
ZHENG gang, REN Yan-hua. Effects of time-effect of pile’s bearing capacity on pile-soil interaction and on settlement of pile-raft foundation[J]. 2003, 24(1).
DOI:
ZHENG gang, REN Yan-hua. Effects of time-effect of pile’s bearing capacity on pile-soil interaction and on settlement of pile-raft foundation[J]. 2003, 24(1).DOI:
Effects of time-effect of pile’s bearing capacity on pile-soil interaction and on settlement of pile-raft foundation
Pile loading tests of two bored piles of length 47m in soft soil are carried out for 28 days and 1 750 days after they are constructed. In-situ test shows that the ultimate bearing capacity of these two single piles increased about 30 %. The mechanism of time-effect of bearing capacity of pile is analyzed; and method of analyzing the effects of the time-effect of a pile’s bearing capacity on pile-soil interaction of pile-raft foundation is discussed with an engineering example.