Analysis on Deaerating Heater System of Power Station of 4 Million t/a Coal Liquid Project in Shenhua Ningxia Coal Industry Group
摘要
为了更好地优化神华宁煤400万t/a煤炭间接液化项目给水系统
提高给水系统除氧能力
分析了神华宁煤烯烃公司自备电厂给水系统溶解氧长久不合格的原因
指出化工厂自备电厂与普通电厂的不同
给出了自备电厂给水溶氧控制方法的建议。
Abstract
To get better water supply system in Shenhua Ningxia 4 million t/a coal liquid and improve ability of removing the oxygen
the long qualified reasons of the oxygen in water supply system for power plant in Olefins Company of Shenhua Ningxia Coal Industry Group were analyzed.The different of chemical plant power plant between ordinary plants was pointed out
and some ways to remove the oxygen in water supply system in the Power Plant in Chemical Industry were given.