COMPARISON BETWEEN TWO TYPICAL CONTROL MODES IN IP CYLINDER STARTING OF UNIT
|更新时间:2025-09-28
|
COMPARISON BETWEEN TWO TYPICAL CONTROL MODES IN IP CYLINDER STARTING OF UNIT
Thermal Power GenerationVol. 39, Issue 2, Pages: 5-9(2010)
作者机构:
1. 西北电力建设调试施工研究所
2. 西北电力设计院
作者简介:
基金信息:
DOI:
CLC:TK267
Published:2010
稿件说明:
移动端阅览
XIONG Wei1, ZHANG Lie1, WANG Wei21.North-west China Electric Power Construction and Debugging Research Institute. COMPARISON BETWEEN TWO TYPICAL CONTROL MODES IN IP CYLINDER STARTING OF UNIT[J]. Thermal power generation, 2010, 39(2): 5-9.
DOI:
XIONG Wei1, ZHANG Lie1, WANG Wei21.North-west China Electric Power Construction and Debugging Research Institute. COMPARISON BETWEEN TWO TYPICAL CONTROL MODES IN IP CYLINDER STARTING OF UNIT[J]. Thermal power generation, 2010, 39(2): 5-9.DOI:
COMPARISON BETWEEN TWO TYPICAL CONTROL MODES IN IP CYLINDER STARTING OF UNIT
The units with IP cylinder starting have been widely used in recent years
among them
the 330 MW units manufactured from Beijing Heavy Electric Machine Works being in the majority
the others being 600 MW units manufactured by East China Turbine Works.The features of control mode in IP cylinder starting for above-mentioned two kinds of units have been analysed and compared
results show that the manupulation in IP cylinder starting operation for 300 MW units manufactured from Beijing Heavy Electric Machine Works is simple
enhancing the automation level of said units
while in IP cylinder starting of 600 MW units manufactured from East China Turbine Works
there isn't clear requirement to load for cylinder change-over