APPLICATION OF LOAD-PREESTIMATING SIGNAL IN THE COORDINATED CONTROL SYSTEM OF UNITS
|更新时间:2025-09-28
|
APPLICATION OF LOAD-PREESTIMATING SIGNAL IN THE COORDINATED CONTROL SYSTEM OF UNITS
Thermal Power GenerationVol. 39, Issue 6, Pages: 53-55(2010)
作者机构:
华能铜川电厂
作者简介:
基金信息:
DOI:
CLC:TK323
Published:2010
稿件说明:
移动端阅览
LI Chengming, SONG Zhiqiang, CHENG Junjun Huaneng Tongchuan Power Plant. APPLICATION OF LOAD-PREESTIMATING SIGNAL IN THE COORDINATED CONTROL SYSTEM OF UNITS[J]. Thermal power generation, 2010, 39(6): 53-55.
DOI:
LI Chengming, SONG Zhiqiang, CHENG Junjun Huaneng Tongchuan Power Plant. APPLICATION OF LOAD-PREESTIMATING SIGNAL IN THE COORDINATED CONTROL SYSTEM OF UNITS[J]. Thermal power generation, 2010, 39(6): 53-55.DOI:
APPLICATION OF LOAD-PREESTIMATING SIGNAL IN THE COORDINATED CONTROL SYSTEM OF UNITS
Directing against the problems existing in the coordinated control system of 2×600 MW units in first-phase project of Huaneng Tongchuan Power Plant
i.e.having time delay in main steam pressure control for boilers
being unable to satisfy the requirement of quality index for rapid load variation in the power grid
the optimization of said control system has been carried out.The dynamic state of load-preestimating signal is added into the circuit of boiler steam pressure control of the original coordinated control system
and acting as a feed-forward signal of direct energy balance
and thereby to enhance the response speed of coordinated control system for units to the load variation.Test of automatic generation control(AGC) shows that the coordinated control system of units after optimization has strong load adaptability and fast response speed