DESIGN AND APPLICATION OF A NEW BYPASS CONTROL STRATEGY FOR UNITS
|更新时间:2025-09-28
|
DESIGN AND APPLICATION OF A NEW BYPASS CONTROL STRATEGY FOR UNITS
Thermal Power GenerationVol. 39, Issue 9, Pages: 81-84(2010)
作者机构:
1. 国华浙能发电有限公司
2. 上海电力建设启动调整试验所
3. 西门子电站自动化有限公司
作者简介:
基金信息:
DOI:
CLC:TM31
Published:2010
稿件说明:
移动端阅览
ZHU Jienan1, WU Yongcun1, JIN Qilin2, et al. DESIGN AND APPLICATION OF A NEW BYPASS CONTROL STRATEGY FOR UNITS[J]. Thermal power generation, 2010, 39(9): 81-84.
DOI:
ZHU Jienan1, WU Yongcun1, JIN Qilin2, et al. DESIGN AND APPLICATION OF A NEW BYPASS CONTROL STRATEGY FOR UNITS[J]. Thermal power generation, 2010, 39(9): 81-84.DOI:
DESIGN AND APPLICATION OF A NEW BYPASS CONTROL STRATEGY FOR UNITS
Directing against the problems existing in many power plants
i.e.the bypass system of units is unable to bring its protective effects into full play
and only used as a drain valve of boiler and steam turbine in the stage of start-up or shutdown of units
a new bypass control strategy has been designed
which devides the HP-bypass into five control modes
the whole process automatic control of bypass system
from start-up of unit to connet the unit onto power grid
and returned again to sectionalization and shutdown of boiler
can be realized.Through calculation of steam's enthalpy drop before and after the LP-bypass system
the quantity of desuperheating water required by the LP-pass system can be precisely pre-estimated
thereby the exhaust steam from the LP-bypass system can be ensured to satisfy the requirement in operation of condenser.The above-mentioned control strategy has been applied onto an ultra-supercritical 1 000 MW unit in second-phase project of Ninghai Power Plant
the fast cut back (FCB) of unit without boiler shutdown being realized;after finishing assessment test of the bypass system
the unit is reconnected onto the power grid within 0 min
and the load of unit being increased to 480 MW after 15 min.