OPTIMIZED RETROFIT OF WASTEWATER TREATMENT SYSTEM IN WET DESULPHURIZATION OF 600 MW UNIT
|更新时间:2025-09-28
|
OPTIMIZED RETROFIT OF WASTEWATER TREATMENT SYSTEM IN WET DESULPHURIZATION OF 600 MW UNIT
Thermal Power GenerationVol. 40, Issue 10, Pages: 62-65(2011)
作者机构:
大唐王滩发电有限责任公司
作者简介:
基金信息:
DOI:
CLC:X703
Published:2011
稿件说明:
移动端阅览
NIE Pengfei Datang Wangtan Power Generation Co Ltd. OPTIMIZED RETROFIT OF WASTEWATER TREATMENT SYSTEM IN WET DESULPHURIZATION OF 600 MW UNIT[J]. Thermal power generation, 2011, 40(10): 62-65.
DOI:
NIE Pengfei Datang Wangtan Power Generation Co Ltd. OPTIMIZED RETROFIT OF WASTEWATER TREATMENT SYSTEM IN WET DESULPHURIZATION OF 600 MW UNIT[J]. Thermal power generation, 2011, 40(10): 62-65.DOI:
OPTIMIZED RETROFIT OF WASTEWATER TREATMENT SYSTEM IN WET DESULPHURIZATION OF 600 MW UNIT
The formation of wastewater and source of various pollutants from the limestone/gypsum wet desulphurization of 600 MW unit in one power plant have been analysed in detail
the technological process of wastewater treatment system for wet desulphurization being presented
and the problems existing in practical operation of the wastewater treatment system being summarized up and concluded.Through analysis
the corresponding retrofit measures have been put forward as in the following:adopting the highly effective swirler;installing additionallty the presettling tank;increasing revolution speed of agitator in the neutralization basin
the settling basin
and the flocculation basin;installing additionally mechanical agitator in the aerating basin for wastewater regulation;retrofitting structure of the clarification basin;adjusting the dosage to improve function of the press-filter;as well as increasing the number of detecting instruments ets..After the optimized retrofitting
the wastewater treatment system for desulphurization has been in normal and stable operation at present
all indices of discharges tally well with the standard.