STEAM COMBINATION AND DECOMPOSITION ON M701F SERIES GAS TURBINE “2 ON 1” UNIT
|更新时间:2025-09-28
|
STEAM COMBINATION AND DECOMPOSITION ON M701F SERIES GAS TURBINE “2 ON 1” UNIT
Thermal Power GenerationVol. 41, Issue 8, Pages: 65-68(2012)
作者机构:
西安热工研究院有限公司
作者简介:
基金信息:
DOI:
CLC:TM621.3
Published:2012
稿件说明:
移动端阅览
AN Zongwu, XIN Junfang, CHEN Hao Xi'an Thermal Power Research Institute Co.. STEAM COMBINATION AND DECOMPOSITION ON M701F SERIES GAS TURBINE “2 ON 1” UNIT[J]. Thermal power generation, 2012, 41(8): 65-68.
DOI:
AN Zongwu, XIN Junfang, CHEN Hao Xi'an Thermal Power Research Institute Co.. STEAM COMBINATION AND DECOMPOSITION ON M701F SERIES GAS TURBINE “2 ON 1” UNIT[J]. Thermal power generation, 2012, 41(8): 65-68.DOI:
STEAM COMBINATION AND DECOMPOSITION ON M701F SERIES GAS TURBINE “2 ON 1” UNIT
For thermal system of M701F4 series "2 on 1" split-shaft unit with gas-steam combined cycle in Huaneng Beijing thermal power plant
its features and start-up mode were introduced.Practical applications show that
problems such as big difference in temperature between upper and lower casing
difficulty in bypass control and high pressure in IP(intermediate pressure) exhaust steam etc.which occur during the steam combination
can be solved by method of combining IP steam first
then HP(high pressure) steam
and LP(low pressure) steam finally.After the improvement of bypass control
the unit can be easily operated during the combination and decomposition of steam.The load is stable and satisfies the request that the unit should start-up and shut-down quickly during peak regulation or two-shift operation.