Feasibility of closed circulating water waste heat utilization in 600MW supercritical unit
Thermal Power GenerationVol. 42, Issue 3, Pages: 5-7(2013)
作者机构:
华电电力科学研究院
作者简介:
基金信息:
DOI:
CLC:TK115;TK267
Published:2013
稿件说明:
移动端阅览
LUO Haihua, WANG Baoyu, ZHAO Yuzhu, et al. Feasibility of closed circulating water waste heat utilization in 600MW supercritical unit[J]. Thermal power generation, 2013, 42(3): 5-7.
DOI:
LUO Haihua, WANG Baoyu, ZHAO Yuzhu, et al. Feasibility of closed circulating water waste heat utilization in 600MW supercritical unit[J]. Thermal power generation, 2013, 42(3): 5-7.DOI:
Feasibility of closed circulating water waste heat utilization in 600MW supercritical unit
摘要
针对某超临界600MW机组闭式循环水夏、秋季节温度高给机组带来安全隐患等问题
提出了采用压缩式热泵替代板式换热器对闭式循环水进行冷却
并排挤汽轮机第8级部分抽汽的方案。分析结果表明
系统改造后全年可增加收入417.11万元
6.23年可收回投资
经济性较好
投资回报期较短。
Abstract
High temperature closed circulating water in summer and autumn brought security risk of a supercritical 600 MW unit.Thus
countermeasure that replacing the plate heat exchanger by compression heat pump to cool the closed circulating water
and pushing out partial extraction in the 8th stage of the turbine was put forward.The economy of this scheme was analyzed and it showed that
the annual income of the improved system can be increased by 4.171 1×106 yuan
and the investment can be recovered within 6.23 years.