Performance analysis on regenerative system after cogeneration transformation of a condensing unit
Thermal Power GenerationVol. 42, Issue 9, Pages: 16-19(2013)
作者机构:
1. 上海电力学院能源与机械工程学院
2. 华电电力科学研究院
作者简介:
基金信息:
DOI:
CLC:TU995
Published:2013
稿件说明:
移动端阅览
ZHENG Puyan, CHAI Guoxu, YAO Xiuping, et al. Performance analysis on regenerative system after cogeneration transformation of a condensing unit[J]. Thermal power generation, 2013, 42(9): 16-19.
DOI:
ZHENG Puyan, CHAI Guoxu, YAO Xiuping, et al. Performance analysis on regenerative system after cogeneration transformation of a condensing unit[J]. Thermal power generation, 2013, 42(9): 16-19.DOI:
Performance analysis on regenerative system after cogeneration transformation of a condensing unit
摘要
以某330MW机组为例
分析了凝汽式机组供热改造后回热系统的变化
采用夹点理论对该机组的回热换热进行网络优化。结果表明
在该机组供热改造的同时进行回热系统同步改造
设置外置式过热蒸汽冷却器
其理论最佳方案可使系统效率比回热系统不同步改造的方案提高0.31%
额定进汽量下机组发电功率增加3MW。实际改造中需要考虑系统可靠性和投资成本
不需要对所有过热度高的抽汽设置外置式过热蒸汽冷却器
再热器前、后的抽汽具有较高的过热度
对系统效率提高明显
需要优先考虑。
Abstract
A 330MW condensing unit was taken as the example to analyze the performance change of regenerative system after the cogeneration retrofit.The pinch theory was employed to carry out network optimization on heat transfer in this regeneration system.The results showed that
if conducting the regeneration system transformation simultaneously during the heat supply retrofit
and setting up the external superheated steam cooler
the system efficiency and generation capacity under rated inlet steam amount condition can be enhanced by 0.31%and 3MW
respectively.During the practical transformation
the reliability and investment cost should be considered
and the external superheated steam cooler is not necessary for all extraction steam with high superheating ratio.The steam extracted before and after the reheater
which has high superheat ratio and can enhance the system efficiency effectively