HU Xiuli 1, LIU Limei 1, FU Wenling2 1.Shenhua Beijing Guohua Electric Power Co.. Heat exchange component transformation for GGH in desulfurization system of a thermal power plant[J]. Thermal power generation, 2013, 42(8): 153-155.
DOI:
HU Xiuli 1, LIU Limei 1, FU Wenling2 1.Shenhua Beijing Guohua Electric Power Co.. Heat exchange component transformation for GGH in desulfurization system of a thermal power plant[J]. Thermal power generation, 2013, 42(8): 153-155.DOI:
Heat exchange component transformation for GGH in desulfurization system of a thermal power plant
The running resistance in gas-gas heat(GGH)exchanger of desulfurization system of the No.1unit in Beijing Thermal Power Plant was too high.Several factors were considered as the main reasons
such as the excess gas flow in desulfurization system(compared with the design value)
unreasonable strip shape selection for heat exchange component in GGH
increasing viscosity of ash in flue gas
and relatively low pressure at inlet and outlet of the desulfurization booster fan.Thus
transformation of heat exchange component in GGH was conducted.The DNF thin steel corrugated plate was changed into L type large channel corrugated plate.For the improved unit
the net gas temperature can reach the design value(80℃)
and the running resistance of the GGH and the booster fan current were both kept at a relatively low level
under various loads conditions.When the boiler ran with full load
under the condition that the net gas outlet temperature was 89℃and the resistance at one side of the GGH was 270Pa(design value 500Pa)