Optimization design of steam turbine with double-reheat in a 1 350MW ultra-supercritical unit
|更新时间:2025-09-28
|
Optimization design of steam turbine with double-reheat in a 1 350MW ultra-supercritical unit
Thermal Power GenerationVol. 45, Issue 1, Pages: 110-116(2016)
作者机构:
1. 华北电力大学能源与动力机械工程学院
2. 国电科学技术研究院
作者简介:
基金信息:
DOI:
CLC:TM621
Published:2016
稿件说明:
移动端阅览
ZHANG Xiaoling, YAN Weiping, LIU Liheng, et al. Optimization design of steam turbine with double-reheat in a 1 350MW ultra-supercritical unit[J]. Thermal power generation, 2016, 45(1): 110-116.
DOI:
ZHANG Xiaoling, YAN Weiping, LIU Liheng, et al. Optimization design of steam turbine with double-reheat in a 1 350MW ultra-supercritical unit[J]. Thermal power generation, 2016, 45(1): 110-116.DOI:
Optimization design of steam turbine with double-reheat in a 1 350MW ultra-supercritical unit
To investigate the influence of shaft arrangements and shaft speed on efficiency and economy of the 1 350 MW ultra-supercritical double reheat unit
schemes of four different steam turbine types were built to carry out simulation and calculations.The effects of exhausting outlet number
single-and doubleshaft arrangement(cross-compound or tandem-compound)and shaft speed selection on the unit's efficiency and economy were analyzed.The results show that
for the 1 350 MW ultra-supercritical double-reheat condensing unit
a tandem-compound 4-flow steam turbine with a primary rotor portion running at 3 000 rpm and a secondary rotor portion running at 1 500 rpm is the best scheme
the plant net efficiency can reach up to 46.01%.Then the second choice is the scheme of a cross-compound 6-flow steam turbine with rotor portion running at full-speed.Due to the technical limitation and investment economic weakness
it is better not adopt the scheme of a cross-compound 4-flow steam turbine with rotor portion running at full speed and the scheme of a tandem-compound 6-flow steam turbine with a primary rotor portion running at3000 rpm and a secondary rotor portion running at 1 500 rpm.