Design scheme and application of APS system in an ultra-supercritical 1000MW unit with double-reheat cycle
|更新时间:2025-09-28
|
Design scheme and application of APS system in an ultra-supercritical 1000MW unit with double-reheat cycle
Thermal Power GenerationVol. 46, Issue 2, Pages: 125-129(2017)
作者机构:
1. 北京国电智深控制技术有限公司
2. 国电泰州发电有限公司
3. 华东电力设计院有限公司
作者简介:
基金信息:
DOI:
CLC:TM621
Published:2017
稿件说明:
移动端阅览
NIU Haiming, WU Dongli, YANG Shuang, et al. Design scheme and application of APS system in an ultra-supercritical 1000MW unit with double-reheat cycle[J]. Thermal power generation, 2017, 46(2): 125-129.
DOI:
NIU Haiming, WU Dongli, YANG Shuang, et al. Design scheme and application of APS system in an ultra-supercritical 1000MW unit with double-reheat cycle[J]. Thermal power generation, 2017, 46(2): 125-129.DOI:
Design scheme and application of APS system in an ultra-supercritical 1000MW unit with double-reheat cycle
The design scheme and structure of automatic power plant start-up and shut-down control system(APS)for an ultra supercritical 1 000 MW unit with double-reheat cycle in Taizhou Power Plant was presented.The basic points and attentions during the accomplishment of the APS were introduced
which includes the design of the DCS hardware
device driver level logic
sequence control standard logic and human interface.It pointed out that the key points during the APS design are the superheated steam temperature control
the primary reheate stem temperature control
the secondary reheat steam temperature control and the third bypass control during the start-up and shut-down process of the unit.Moreover
the automatic scheme for the whole process of steam temperature control and bypass control were given.It indicated that the application of the APS reduces the start time and the power consumption rate
improves the economic efficiency
and its design and the function of the break-point
steam temperature and bypass full automatic control have a certain value to other ultra-supercritical units with double-reheat cycle.