Research on Unit Commitment Considering Steady State Frequency Constraints of Isolated Grids with High Permeability Wind Power
|更新时间:2025-12-08
|
Research on Unit Commitment Considering Steady State Frequency Constraints of Isolated Grids with High Permeability Wind Power
Vol. 44, Issue 4, Pages: 1311-1318(2018)
作者机构:
1. 武汉大学电气工程学院
2. 太阳能高效利用湖北省协同创新中心
3. 华中电力调控分中心
作者简介:
基金信息:
DOI:
CLC:
Published Online:10 May 2018,
Published:2018
稿件说明:
移动端阅览
YE Jing, LIN Tao, XU Xialing, et al. Research on Unit Commitment Considering Steady State Frequency Constraints of Isolated Grids with High Permeability Wind Power[J]. 2018, 44(4): 1311-1318.
DOI:
YE Jing, LIN Tao, XU Xialing, et al. Research on Unit Commitment Considering Steady State Frequency Constraints of Isolated Grids with High Permeability Wind Power[J]. 2018, 44(4): 1311-1318.DOI:
Research on Unit Commitment Considering Steady State Frequency Constraints of Isolated Grids with High Permeability Wind Power
摘要
孤立电网具有各次备用容量小、自平衡能力差的特点。为了提高风能的利用率
在保障稳态频率约束的前提下
采用综合利用一、二次备用的方法。提出了考虑稳态频率约束的系统最大可调备用容量的概念
建立了考虑稳态频率约束的机组组合优化模型。以常规机组发电成本最小和系统消纳风能最大为多目标
并通过扩展ε约束法对模型进行求解。改造后含高渗透率风电的孤立电网10机系统的计算结果表明
所提模型通过有效利用系统中各次备用
在满足系统稳态频率约束的同时
有较好的经济性以及风电的消纳能力。
Abstract
An isolated power grid has a small reserve.In order to increase the permeability of wind power
we proposed a concept of the maximum adjustable reserve capacity considering the steady-state frequency constraint
and established a unit commitment model considering steady state frequency constraints.Minimizing the fuel cost and maximizing absorption of wind power were considered as objective functions
and the augmented-ε-constraint method was used to solve the multi-objective problem.The effectiveness
economic efficiency
and energy conservation of the proposed model are verified on an isolated power grid of ten-generators.Case analysis of an isolated power gird verifies the effectiveness