Optimization Model of Distribution Network Maintenance Plan Based on Equipment Condition Evaluation and Grid Loss Risk
|更新时间:2025-12-08
|
Optimization Model of Distribution Network Maintenance Plan Based on Equipment Condition Evaluation and Grid Loss Risk
Vol. 44, Issue 11, Pages: 3751-3759(2018)
作者机构:
1. 中国电力科学研究院有限公司
2. 华北电力大学电气与电子工程学院
作者简介:
基金信息:
DOI:
CLC:
Published Online:22 November 2018,
Published:2018
稿件说明:
移动端阅览
LI Erxia, KANG Chaoqun, LI Yuling, et al. Optimization Model of Distribution Network Maintenance Plan Based on Equipment Condition Evaluation and Grid Loss Risk[J]. 2018, 44(11): 3751-3759.
DOI:
LI Erxia, KANG Chaoqun, LI Yuling, et al. Optimization Model of Distribution Network Maintenance Plan Based on Equipment Condition Evaluation and Grid Loss Risk[J]. 2018, 44(11): 3751-3759.DOI:
Optimization Model of Distribution Network Maintenance Plan Based on Equipment Condition Evaluation and Grid Loss Risk
Traditional maintenance plans of distribution network focus on grid structure and load while ignoring equipment difference and real-time equipment status. In order to solve the problems
we established an optimization model of distribution network maintenance plan based on equipment condition evaluation and grid loss risk calculation
put forward a calculation method of the matrix between an equipment health index and a failure rate in the future analysis time
and presented the key parameters. Based on the dynamic failure rate and the distribution network topology
the minimum road method was adopted to obtain the failure rate and the load point failure time of the whole distribution network under normal conditions and maintenance conditions. Then
the risk model of the loss of a power grid caused by failure
the loss of equipment failure
the loss of the power grid caused by maintenance
and the loss of the equipment caused by maintenance were established based on the risk of the loss of the power supply
the importance of the load point
the equipment value
and the maintenance cost. The results show that the optimization model proposed in the paper comprehensively considers the risk decision value calculated by the above risk model
realizing the optimization of the maintenance plan. Meanwhile
the historical average failure rate in the process of the traditional maintenance plan was replaced by the dynamic change failure rate
overcoming the traditional condition evaluation disadvantages caused by the maintenance without taking the weak power distribution network into account. Finally
the model was used to calculate an actual case of a distribution network in Nanjing
and the decision values of distribution network risk were obtained.The calculation results show that the risk value of the distribution network is not necessarily determined by single risk factor such as multiple equipment
heavy load
and late maintenance time
the overall cost of the maintenance plan determined by the model is lower than other schemes and it meet the needs of actual projects. The research results validate the feasibility of the optimization of the distribution network maintenance plan based on the equipment status evaluation
and the proposed method is also applicable to the maintenance plan optimization of the higher voltage level network.