Abstract:
IEC 61850 is one of the core standards of smart substation. On the basis of Ed1.0, the International Electro-technical Commission (IEC) released the second edition of IEC 61850 (IEC 61850 Ed2.0) with a wider range of applications and better functional mechanisms. In order to apply general object-oriented substation event (GOOSE) which is one of the core functions of IEC 61850 Ed2.0 to engineering practice, by comparing GOOSE Ed2.0 and Ed1.0, this paper proposes an implementation strategy of IEC 61850 Ed2.0 GOOSE from the aspects of general idea, configuration method and the main logic implementation based on combing and analyzing the role and meaning of their different points, The IEC 61850 Ed2.0 GOOSE module is implemented and applied in the practical substation projects.