丁相城, 李利凯. 越南某海上风电海底电缆抢修施工工序及质量控制[J]. 电力勘测设计, 2024, (1): 22-25,76. DOI: 10.13500/j.dlkcsj.issn1671-9913.2024.01.005
引用本文: 丁相城, 李利凯. 越南某海上风电海底电缆抢修施工工序及质量控制[J]. 电力勘测设计, 2024, (1): 22-25,76. DOI: 10.13500/j.dlkcsj.issn1671-9913.2024.01.005
DING Xiang-cheng, LI Li-kai. Submarine Cable Repair Procedure and Quality Control of Offshore Wind Power Plant in Vietnam[J]. Electric Power Survey & Design, 2024, (1): 22-25,76. DOI: 10.13500/j.dlkcsj.issn1671-9913.2024.01.005
Citation: DING Xiang-cheng, LI Li-kai. Submarine Cable Repair Procedure and Quality Control of Offshore Wind Power Plant in Vietnam[J]. Electric Power Survey & Design, 2024, (1): 22-25,76. DOI: 10.13500/j.dlkcsj.issn1671-9913.2024.01.005

越南某海上风电海底电缆抢修施工工序及质量控制

Submarine Cable Repair Procedure and Quality Control of Offshore Wind Power Plant in Vietnam

  • 摘要: 介绍越南某海上风电施工过程中损坏的海底电缆抢修施工工序,以及各工序质量控制要点,为类似海底电缆抢修工作安排及质量管理提供必要参考。

     

    Abstract: This article introduced the emergency repair construction procedure of submarine cable damaged in the construction process of an offshore wind power plant in Vietnam, and described each procedure and key points of quality control, which can provide necessary reference for similar submarine cable emergency repair work and quality management.

     

/