孙巍, 蔡建平, 韩麟. 濒海软弱地基场地翻车机室地下部分结构设计与施工方案选型[J]. 电力勘测设计, 2021, (S2): 40-44. DOI: 10.13500/j.dlkcsj.issn1671-9913.2021.S2.006
引用本文: 孙巍, 蔡建平, 韩麟. 濒海软弱地基场地翻车机室地下部分结构设计与施工方案选型[J]. 电力勘测设计, 2021, (S2): 40-44. DOI: 10.13500/j.dlkcsj.issn1671-9913.2021.S2.006
SUN Wei, CAI Jian-ping, HAN Lin. Design and Construction Scheme Selection of Underground Structure of Rotary Dumper Room in Soft Foundation Site Near Sea[J]. Electric Power Survey & Design, 2021, (S2): 40-44. DOI: 10.13500/j.dlkcsj.issn1671-9913.2021.S2.006
Citation: SUN Wei, CAI Jian-ping, HAN Lin. Design and Construction Scheme Selection of Underground Structure of Rotary Dumper Room in Soft Foundation Site Near Sea[J]. Electric Power Survey & Design, 2021, (S2): 40-44. DOI: 10.13500/j.dlkcsj.issn1671-9913.2021.S2.006

濒海软弱地基场地翻车机室地下部分结构设计与施工方案选型

Design and Construction Scheme Selection of Underground Structure of Rotary Dumper Room in Soft Foundation Site Near Sea

  • 摘要: 结合某工程濒海软弱地基场地翻车机室,对其地下部分的常规结构设计方案与沉井结构设计方案、以及相应的各种施工方案进行分析比较,并对其技术经济指标进行对比。分析结果表明,对于此类工程地质条件的场地,翻车机室地下部分采用沉井结构设计和施工方案是较为适宜的。

     

    Abstract: Combined with the rotary dumper room of a coastal soft foundation site,this paper analyzes and compares the conventional structural design scheme of its underground part with the open caisson structural design scheme,as well as various corresponding construction schemes,and compares its technical and economic indexes.The analysis results show that for the site with such engineering geological conditions,the open caisson structure design and construction scheme for the underground part of the car dumper room is more appropriate.

     

/