三峡电站伸缩节制造水压试验技术
摘要
三峡电站引水压力钢管伸缩节
是目前国内水电行业最大的波纹管水封双套筒式伸缩节
其结构庞大
且制造尺寸精度要求极高
为了检验伸缩节的制作质量、进一步验证结构设计强度及波纹管与水封的密封性
根据设计要求必须进行波纹管与水封的水压试验
文章就三峡伸缩节的水压试验的试验过程与技术作简单介绍。
Abstract
The expansion joints of diversion penstocks for Three Gorges Hydropower Station are of the biggest ones with telescopic water seal corrugated pipe in China at present. The fabricating accuracy requirements are very high. In order to verify the fabricating quality and the design strength of the expansion joint as well the sealing ability of the corrugated pipe and water seal
the water pressure test must be done. The paper introduces the technique and process of the water pressure test.